Interconnection methods in plain English
Where solar ties in is a code decision the busbar math forces, and the obvious spot is often the one the rules rule out.
Answers the Interconnection method question during setup.
Everything in this article can be read with the enclosure door open and every metal cover left in place. Do not remove a cover, and do not open a meter enclosure. If a number is not visible that way, it is a question for a licensed electrician, not something to go looking for.
“Interconnection is utility paperwork. On the drawing it is just where the wire lands, and any spot is fine as long as the breaker fits.”
The common misreading. Here is what is actually true.
The word describes two different things and that is where the confusion starts. There is the utility process, the application and the approval, and there is the physical decision about where the solar conductors connect to the building. This article is about the second one.
The choice is constrained. A breaker that physically fits into the panel does not mean the connection is allowed, because the limit is not the breaker, it is the busbar it clamps onto.
The three methods
Backfeed breaker, sometimes just called the 120 percent rule connection: solar lands on a breaker in the panel like any other circuit, just running the other direction. It is the simplest and the most common. Note that the method list also carries a separate option named Load Side Tap, which is a different thing covered below.
Supply side: solar connects on the utility side of the service disconnect, between the meter and whatever the first shut-off is. On a service with a separate disconnect that means between the meter and the disconnect, not between the disconnect and the panel. The busbar limit does not apply because no busbar is involved, but other limits do: the output is bounded by the service rating, the tap conductors have their own sizing rules, and the connection brings its own service disconnect for the solar, with its own bond and grounding electrode connection. It always means an electrician working on conductors that stay live until the utility pulls the meter.
Load side tap, also called a feeder or feed-through tap: solar connects to the conductors running between the service and a downstream panel rather than landing on a busbar. The busbar rules are replaced by a conductor test, not removed. The feeder has to be rated for the main breaker plus 125 percent of the solar output, and an existing dwelling feeder sized under the 83 percent allowance often is not. Check it before promising it.
What the 120 percent rule bounds
For a backfeed breaker, the main breaker rating plus 125 percent of the inverter's continuous output current cannot exceed 120 percent of the busbar rating. On a 200A busbar that is 240 amps of total supply, and a 200A main leaves 40. The solar breaker itself is then sized at the next standard size at or above that same 125 percent figure. The allowance also requires the solar breaker at the opposite end of the bus from the main, plus a permanent label saying so.
An MLO service panel is a different animal. With the service conductors landing straight on the lugs there is no overcurrent device ahead of the bus at all, and the code lets each breaker in that panel be one of the service disconnects. A solar breaker there is therefore on the supply side by definition, so the 120 percent rule does not govern it and the limit is the service ampacity instead. Do not force the busbar math onto it.
That exemption is about what is ahead of the bus, not about the missing main. An MLO subpanel, or an MLO panel fed from a meter-main, does have a breaker protecting its busbar, and there the arithmetic runs normally with that feeder breaker as the first term.
When the arithmetic does not leave enough room, there are four moves: shrink the main breaker to buy headroom, upgrade the panel to a larger busbar, move to a supply-side connection where the busbar limit does not apply, or add a listed power control system that actively limits the combined current onto the bus. Reducing the solar is the fifth and the one nobody wants. Each has its own test to pass.
How to get the answer
You can work out which methods are even available before choosing one, from two numbers you can read with every cover in place.
- 1Read the busbar rating off the door label and the main breaker rating off its handle.
- 2Multiply the busbar by 1.2 and subtract the main breaker rating. What is left is the largest value that 125 percent of the inverter output may reach, and only if the solar breaker can physically sit at the far end of the bus from the main.
- 3Take the inverter's continuous AC output current off its datasheet and multiply by 1.25. If that is comfortably under the headroom, backfeed is available. Compare against the current, not against a breaker size, or you will reject designs the code allows.
- 4If the panel is MLO, ask what is ahead of its busbar before doing any arithmetic. Service conductors landing on the lugs with nothing protecting them means an MLO service panel: every breaker is a service disconnect, solar goes in on the supply side, and this calculation does not apply. A breaker feeding it from a meter-main or a disconnect means the rule does apply, with that breaker as the first term.
- 5If it does not fit, the job is a supply-side connection, a feeder tap, a bigger busbar, a smaller main, a power control system, or less solar. Flag it rather than forcing the breaker in.
This is guidance for reading equipment that is already visible and for describing it on a drawing. It is not instruction for electrical work. Any work on service equipment, panels, or conductors is for a licensed electrician, and local code and utility rules govern.
Related guides
Every one of these questions is asked once, in setup.
The editor asks for what it needs, explains why it needs it, and does the engineering from there.
Try the free editor