Solar installations in Milton, Florida, must adhere to specific design parameters set by Santa Rosa County. Understanding these requirements is the first step toward a successful permit application.
Requirements at a glance
- Design wind speed
- 150 mph (ASCE)
- Exposure category
- B
- Ground snow load
- 0 psf
- High-velocity hurricane zone
- No
- Submission format
- Digital submission
- Separate discipline files
- No
What Milton expects on a solar permit
The jurisdiction requires designs to account for a wind speed of 150 mph and exposure category B. The ground snow load is 0 psf. All permit applications must be submitted through a digital delivery process.