NEC Compliance
The solar 120% rule, done right NEC 705.12 across the 2017, 2020, and 2023 cycles
A precise, installer-focused guide to load-side busbar interconnection, from the engineering team at Solar Design Lab.
Last updated May 2026.
Quick answer
The solar 120% rule limits the combined current feeding a panel busbar from the utility and the PV system to 120% of the busbar's rated ampacity, when the solar backfeed breaker is placed at the opposite end of the busbar from the main breaker. The formula is: (125% of inverter output current) + (main breaker rating) must be less than or equal to (120% of the busbar rating). On a standard 200A busbar with a 200A main, that allows a 40A solar backfeed breaker, which supports a roughly 32A (about 7.6 kW) inverter. The rule lives in different NEC subsections depending on the code cycle: 705.12(D)(2) in 2014, 705.12(B)(2)(3)(b) in 2017, 705.12(B)(3)(2) in 2020, and 705.12(B)(2) in 2023.
Key facts at a glance
- Formula: (1.25 × inverter output current) + main breaker ≤ 1.20 × busbar rating.
- The 125% multiplier is mandatory and is the single most common missing element in plan-check redlines.
- Placement is load-bearing: the backfeed breaker must be at the opposite end of the busbar from the main, with a permanent "do not relocate" label.
- Citation moves by cycle: 2017 = 705.12(B)(2)(3)(b); 2020 = 705.12(B)(3)(2); 2023 = 705.12(B)(2). Always cite the cycle your AHJ has adopted.
- MLO panels are exempt: a main-lug-only panel has no main breaker bounding the bus, so the 120% rule does not apply.
- It applies to every busbar in the backfeed path, including subpanels and feed-through conductors, not just the main panel.
- Alternatives when it fails: derate the main, use the sum rule, tap supply-side (705.11), or use a listed Power Control System / EMS (705.13).
On this page
- 1.What the solar 120% rule is
- 2.The citation lineage (2014 to 2023)
- 3.Why 120%, and why "opposite end"
- 4.The load-side methods under 705.12(B)
- 5.The MLO exception
- 6.It applies to every busbar in the path
- 7.Worked examples
- 8.When it fails: the escalation ladder
- 9.Not the service load calculation
- 10.Backfeed breaker suitability
- 11.Solar plus storage
- 12.How Solar Design Lab handles it
- 13.Permit checklist
- 14.Frequently asked questions
- 15.The takeaway
The 120% rule is one of the most common reasons a residential solar design gets revised before permit submittal, and one of the most common plan-check rejections when it is applied incorrectly. Getting it right at the design stage is the difference between a clean first submission and a redesign.
This guide covers what the rule is, the physics behind it, the exact code citation for each code cycle (this is where most published guides get sloppy), how to run the calculation with worked examples, the panel types that change or remove the rule, how it propagates to subpanels, and every legitimate path when a design fails it.
What is the solar 120% rule?
The 120% rule governs load-side interconnection of a power source, such as solar or storage, to a busbar in a panelboard. It limits the combined current from two sources, the utility through the main breaker and the PV system through a backfeed breaker, to 120% of the busbar's rated ampacity, provided the backfeed breaker is installed at the opposite end of the busbar from the main.
The formula every installer needs:
The 1.25 multiplier is the continuous-current factor from NEC 690.8(A) and (B). It is not optional, and omitting it is one of the most common plan-check redlines in the entire interconnection review. You apply 125% to the inverter's continuous output current, then size the backfeed breaker to the next standard size at or above that value.
On a standard 200A busbar with a 200A main breaker: 1.20 × 200 = 240A allowed, minus the 200A main leaves 40A for the solar backfeed breaker. A 40A breaker supports a continuous PV output of 32A (since 32 × 1.25 = 40), which is roughly a 7.6 kW inverter. It fits exactly.
Maximum continuous PV output by panel configuration
| Busbar rating | Main breaker | Max PV breaker | Max continuous PV output |
|---|---|---|---|
| 100A | 100A | 20A | 16A |
| 150A | 150A | 30A | 24A |
| 200A | 200A | 40A | 32A |
| 225A | 200A | 50A | 40A |
| 225A | 225A | 45A | 36A |
| 400A | 400A | 80A | 64A |
The 225A-busbar-with-200A-main row is the one worth memorizing: that configuration yields 50A of backfeed breaker versus 40A on a standard 200A/200A panel, which is 8A more continuous PV output. On new construction or a full panel replacement, specifying a 225A busbar with a 200A main costs very little and buys meaningful headroom.
The citation lineage: get the code section right for your cycle
This is where most published 120%-rule guides, including some currently ranking, are imprecise, and where a planset earns or loses credibility with a plan reviewer. The 120% rule has lived in different subsections of the NEC in every recent cycle, because Article 705 has been reorganized repeatedly. Citing the wrong subsection for the adopted cycle is a small error that signals a bigger one.
| Code cycle | Citation for the busbar rule | Notes |
|---|---|---|
| NEC 2014 | 705.12(D)(2) | Originated earlier in 690.64(B)(2), moved into 705.12 in the 2014 cycle |
| NEC 2017 | 705.12(B)(2)(3)(b) | The busbar methods sat under (B)(2)(3) |
| NEC 2020 | 705.12(B)(3)(2) | Article 705 reorganized; old 705.12(A) became 705.11, old (B) became the new (B) |
| NEC 2023 | 705.12(B)(2) | Feeder rules moved to 705.12(A), dropping the busbar methods down a subsection level |
The practical takeaway: the 2023 cycle moved the feeder provisions to 705.12(A) and renumbered the busbar methods, so the 120% rule that was 705.12(B)(3)(2) in 2020 is now cited as 705.12(B)(2) in 2023. The physics and the math did not change. Only the numbering did. Many AHJs are still on the 2017 or 2020 cycle, so the correct move is always to cite the subsection for the code edition your jurisdiction has actually adopted, and to confirm that edition before you submit. A planset that cites the right section for the right cycle reads as authoritative. One that cites the 2020 number while claiming 2023 invites a closer look at everything else.
This lineage is not our interpretation. Tesla's own NEC 705 interconnection documentation for Powerwall 3 prints the same three citations for the load-side busbar rule, labeling the configurations as NEC 2017 705.12(B)(2)(3)(b), NEC 2020 705.12(B)(3)(2), and NEC 2023 705.12(B)(2). When the largest residential storage manufacturer and the code text agree on the numbering, a planset that still cites the 2020 section as if it were current is simply behind.
Why 120%, and why "opposite end"
The rule is not arbitrary. It comes directly from the physics of how current flows on a busbar with two sources.
A busbar is rated for a certain ampacity and is normally protected by the main breaker at one end, with the main breaker rating at or below the busbar rating. Add solar through a backfeed breaker and the bus now has two sources feeding it from two directions: the utility through the main, and the PV through the backfeed breaker.
Here is the key physical insight. The loads tap off the bus at points between the two sources. Because of that, no single segment of the busbar ever carries both the full main current and the full PV current at the same time. The only segment that sees current from both sources is the short stretch between the two breakers, and the loads along the way bleed current off before it can accumulate. The 20% of headroom is the code's allowance for that worst-case segment, and it is justified by two things: the physical separation of the sources at opposite ends, and diversity, since solar rarely peaks at the exact instant household loads peak.
This is why the opposite-end placement requirement is load-bearing, not cosmetic. If you move the backfeed breaker next to the main, the source-separation assumption collapses and the 120% math no longer holds. To enforce this, the code requires a permanent label at the backfeed breaker location reading, in substance, "WARNING: POWER SOURCE OUTPUT CONNECTION. DO NOT RELOCATE THIS OVERCURRENT DEVICE." Move the breaker and you void the basis of the calculation, which is exactly why the label exists.
The load-side methods under 705.12(B), and when each applies
The 120% rule is one of several load-side busbar methods. For residential work, three primary methods plus the center-fed dwelling provision cover almost everything.
Method 1: 100% of busbar ampacity (no placement requirement)
The sum of 125% of inverter output current plus the main breaker rating must not exceed the busbar ampacity, with no 120% factor. Because there is no 20% allowance, this is more restrictive, but the backfeed breaker can go anywhere on the busbar with no opposite-end requirement. Useful on large commercial busbars where the math clears the 100% threshold easily and you want placement freedom.
Method 2: 120% of busbar ampacity (the 120% rule)
The standard residential method, and what people mean by "the 120% rule." The backfeed breaker must be at the opposite end of the busbar from the main, and a permanent warning label is required. This is the method that buys you the most backfeed on a typical residential panel.
Method 3: the sum rule (sum of all overcurrent devices)
The sum of all the breaker ratings on the busbar, excluding the main, must not exceed the busbar ampacity. Rarely used for the primary interconnection, but it governs when sizing downstream subpanels and AC collector panels, particularly in string-inverter and multi-source systems.
The center-fed dwelling panelboard provision
This is where a lot of submissions go wrong. A center-fed panelboard in a dwelling is not automatically restricted to Method 1. The NEC has a specific provision (705.12(B)(3)(4) in the 2020 cycle, and 705.12(B)(4) in the 2023 cycle after the busbar methods dropped a subsection level) that allows a connection at either end, but not both ends, of a center-fed dwelling panelboard where 125% of source output current plus the busbar overcurrent device rating does not exceed 120% of the busbar rating. In other words, the 120% math still applies; only the placement logic differs because the main is in the center of the bus rather than at one end.
Practically, a center-fed dwelling panel can often accept a solar backfeed under the 120% calculation, but you must confirm the exact panel configuration, document the specific code basis on the one-line diagram, and verify the AHJ accepts the provision. Some reviewers are unfamiliar with it and will flag a center-fed design reflexively. Have the code section and the calculation ready, and never draw a center-fed panel as if it were a standard end-fed panel.
The MLO exception: when the 120% rule does not apply at all
Here is a case almost no competing guide mentions, and it matters on real jobs. A main-lug-only (MLO) panel has no main breaker on the busbar. The service overcurrent protection is located upstream, not in the panel.
Because the 120% rule is fundamentally about the relationship between the main breaker and the backfeed breaker at opposite ends of the bus, an MLO panel with no main breaker has nothing to bound that calculation in the usual way. The standard 120% rule does not apply to it. Sources connecting to an MLO panel are instead typically evaluated under the 100% rule (Method 1), where 125% of source output plus the busbar overcurrent device must not exceed the busbar ampacity, or under the sum-of-breakers rule (Method 3). Where the panel sits ahead of the service disconnect, supply-side or feeder logic may apply instead. The point is that the panel type determines the method, and an MLO panel is the wrong place to apply the 120% math.
The failure mode to avoid is treating an MLO panel as if the 120% rule applies and either rejecting a perfectly good interconnection or running a calculation that does not fit the panel. Identify whether the panel is main-breaker or main-lug-only before you run any 120% math, because the answer determines whether the rule applies at all.
The 120% rule applies to every busbar in the backfeed path
The rule does not stop at the main panel. It applies to every busbar and every set of feed-through conductors along the path the backfed current travels.
When the PV breaker lands in a main panel that feeds a downstream subpanel, the combined current, utility plus PV, flows through the feed-through conductors to that subpanel. Both those conductors and the subpanel busbar must be rated for the combined current, not just for the original load current. This is one of the most frequently missed issues on retrofit jobs, and a classic source of plan-check comments that appear after the main-panel calculation already checked out. Every panelboard connected in series between the point of interconnection and the service has to satisfy one of the 705.12(B) methods. They do not all have to use the same method, but each one has to pass on its own.
Worked examples
Example 1: standard 200A end-fed panel
Inverter continuous output 32A. 32 × 1.25 = 40A backfeed breaker. 40 + 200A main = 240A. 1.20 × 200A busbar = 240A. 240 ≤ 240, so it passes exactly under Method 2. But only if the busbar is actually rated 200A. If the legend shows a 175A busbar, 1.20 × 175 = 210A, and 240 > 210 fails. Always verify the busbar rating from the panel label; it is not always equal to the main breaker rating.
Example 2: 225A busbar with a 200A main
Inverter continuous output 40A. 40 × 1.25 = 50A backfeed breaker. 50 + 200A main = 250A. 1.20 × 225A busbar = 270A. 250 ≤ 270, passes with room to spare. The 25A of extra busbar over a standard 200A panel translates to 8A more continuous PV output, which is often the difference that lets a larger inverter land without any workaround.
Example 3: center-fed dwelling panel, 200A busbar, 200A main
The main is in the center of the bus, so standard Method 2 does not apply directly. Under the center-fed dwelling provision, a connection at either end (not both) is permitted where 125% of inverter output plus the busbar overcurrent device does not exceed 120% of the busbar: 40 + 200 ≤ 240, which holds. The math matches a standard panel, but you must cite the center-fed provision explicitly on the one-line, confirm AHJ acceptance, and not draw it as a standard end-fed design.
Example 4: a failing design and the derate fix
Inverter continuous output 45A. The backfeed breaker is sized at 125%: 45 × 1.25 = 56.25A, and the next standard breaker size per NEC 240.6(A) is 60A (there is no 55A standard size). On a 200A busbar with a 200A main: 60 + 200 = 260A. The limit is 1.20 × 200 = 240A. Since 260 > 240, the design fails.
One fix is to derate the main breaker to free up busbar headroom. To find the largest compliant main, subtract the PV breaker rating from 120% of the busbar rating, then select the next standard breaker size down per NEC 240.6(A):
For a 200A busbar with a 60A PV breaker: 240 − 60 = 180A. Because 180A is not a standard breaker size (the standard sizes in this range are 150A, 175A, 200A, and 225A), drop to the next standard size down, which is 175A. Verify: 175 + 60 = 235A, and 235 ≤ 240, so a 175A main is compliant. The catch is in the next section: that derate is only viable if the dwelling's Article 220 load calculation supports a 175A main.
When the 120% rule fails: the escalation ladder
A failing 120% calculation does not automatically mean a service upgrade. There is an ordered set of options, from cheapest to most involved.
- 1.Derate the main breaker. Swap to a smaller main to free up busbar headroom: take 120% of the busbar rating, subtract the PV breaker, and select the next standard size down per NEC 240.6(A), as shown in Example 4. This only works if the dwelling's actual load, verified by an NEC Article 220 load calculation, does not require the full main rating. If the calculated load is close to the existing main, downsizing risks nuisance tripping and is not viable. Run the load calc first; this is not a shortcut.
- 2.Use the sum rule (Method 3). Sometimes a design that fails the 120% method passes under the sum-of-breakers method, especially after accounting for the actual breaker population on the bus.
- 3.Connect to a feeder instead of the panel bus. Landing on a feeder rather than a panel busbar invokes a different sub-rule and can resolve the constraint.
- 4.Supply-side tap (NEC 705.11). Connect the PV output ahead of the service main, on the supply side of the service disconnect. Because the 705.12(B) load-side rules only apply on the load side, a supply-side connection bypasses the busbar calculation entirely. The practical limitation: many services use a meter-main combination panel where the tap point sits inside the utility-controlled enclosure, and many utilities and AHJs do not permit field modifications there. Confirm with the utility and AHJ first.
- 5.Power Control System / Energy Management System (NEC 705.13). A listed device actively limits the combined current so the busbar rule becomes moot for the controlled sources. This is the most practical path for larger systems and storage on existing service equipment, and we cover it in depth in our dedicated PCS guide. Note that uncontrolled sources still have to satisfy 705.12.
- 6.Specify correctly from the start. On new construction or a full panel replacement, a 225A busbar with a 200A main costs little and provides real PV headroom without any workaround. The cheapest upgrade is the one you design in before the panel is installed.
The 120% busbar check is not the service load calculation
This distinction trips up a lot of projects. The 705.12 busbar calculation and the NEC Article 220 service load calculation are related but separate, and passing one does not mean passing the other.
The 705.12 busbar calculation is a hardware constraint. It determines whether the physical busbar can carry the combined utility-plus-PV current without overheating, based on busbar ampacity and breaker placement.
The Article 220 service load calculation determines whether the service as a whole is sized for everything the dwelling demands: HVAC, water heating, appliances, EV charging, and the rest.
A project can pass the 120% busbar math and still need a full service upgrade because Article 220 shows the service is undersized for the home's total demand. Conversely, failing the 120% rule does not mean the service is undersized; it may just mean the backfeed breaker is too large for the current panel configuration, solvable by a different method or a main derate without touching the service. These are two different customer conversations, and conflating them leads to either overselling a panel upgrade or underselling what the service actually needs. Before proposing a main-breaker derate as a workaround, run the Article 220 calculation, because if the calculated load is near the existing main, the derate is off the table regardless of what the busbar math allows.
A detail that catches retrofits: backfeed breaker suitability
Easy to miss on panel swaps, and it shows up in plan-check comments more than it should. Under NEC 705.30(D), breakers that are not marked line/load are generally suitable for backfeed. Breakers that carry a line/load marking must be specifically listed and rated for reverse-current use. On a retrofit where an existing breaker is repurposed as the solar backfeed breaker, verify it is appropriate for that use, note it on the drawings, and confirm it in the equipment specifications. It is one of the easier redlines to avoid.
Solar plus storage changes the calculation
Adding battery storage changes the busbar math in a way that catches installers off guard. In most AC-coupled configurations, the battery inverter connects on the AC side as an additional interactive source, not as a load. That means it must be evaluated independently under 705.12, exactly like the PV inverter, and both sources count against the busbar capacity.
The common failure on AC-coupled retrofit storage jobs is treating the battery inverter as an appliance load rather than as a second interactive power source. Both the PV inverter and the battery inverter have to be evaluated against the busbar, and on many panels the combined backfeed is exactly what pushes the design past the 120% limit and toward an EMS / PCS path under 705.13. Storage interconnection also brings NEC Article 706 into play, and the interconnection agreement with the utility may need to be revisited for export-capable configurations.
How Solar Design Lab handles the 120% rule
The 120% rule is simple arithmetic and surprisingly easy to get wrong in ways that cost a permit cycle: a missing 125% multiplier, a busbar rating assumed equal to the main, a breaker drawn at the wrong end, an MLO panel run through a calculation that does not apply, a subpanel in the backfeed path that never got checked, or a code citation that does not match the adopted cycle.
The Solar Design Lab designer runs the busbar check deterministically on every interconnection. It applies the 125% continuous-current factor automatically, uses the busbar rating rather than the main breaker rating as the controlling value, validates backfeed breaker placement for the selected method, and reclassifies a main-lug-only panel out of the 120% calculation when the panel has no main on the bus. When a design fails, it surfaces the escalation options, including computing the largest compliant derated main, and offers the EMS / PCS path under 705.13 when the load-side methods are exhausted. It applies the rule to every busbar in the backfeed path, not just the main panel, so feed-through and subpanel issues surface at design time rather than in plan check. And it cites the correct subsection for the adopted code cycle on the one-line and in the notes, with the required warning label called out automatically.
The goal is the same as everywhere else in the platform: make the correct, code-compliant result the default output of configuring the system, so the redline that was going to cost a week never happens.
See how the designer handles 120% compliance on your planset
120% rule permit checklist: what AHJs look for
What a plan reviewer expects to see on the one-line and electrical sheets:
- The specific 705.12(B) method called out, for the adopted code cycle: Method 1, the 120% rule, the sum rule, the center-fed dwelling provision, or the 705.13 EMS path.
- Busbar ampacity and main breaker rating shown separately, since they are not always the same number.
- Backfeed breaker position documented and consistent with the selected method.
- The 125% multiplier shown in the calculation, not just the resulting breaker size.
- The warning label called out when the 120% rule or the center-fed provision is used.
- Feed-through and subpanel busbar sizing shown when they are in the backfeed path.
- Backfeed breaker confirmed suitable for reverse current on retrofits.
- EMS listing and current-setting documentation if 705.13 is the compliance path.
The most common 120%-related rejections: backfeed breaker drawn at the same end as the main, the 125% multiplier omitted, the warning label not called out, a center-fed panel handled as standard without citing the provision, the busbar rating assumed equal to the main, feed-through conductors undersized for combined current, a retrofit breaker not confirmed for reverse current, and a code citation that does not match the AHJ's adopted cycle.
Frequently asked questions
- What is the 120% rule for solar in simple terms?
- It limits the combined current feeding a panel busbar from the utility and the solar system to 120% of the busbar's rating, when the solar backfeed breaker sits at the opposite end of the busbar from the main. The formula is 125% of inverter output current plus the main breaker rating, which must not exceed 120% of the busbar rating. On a 200A busbar with a 200A main, that allows a 40A solar breaker and about a 32A (7.6 kW) inverter.
- What NEC section is the 120% rule?
- It depends on the code cycle adopted by your jurisdiction. It is 705.12(D)(2) in NEC 2014, 705.12(B)(2)(3)(b) in 2017, 705.12(B)(3)(2) in 2020, and 705.12(B)(2) in 2023. The 2023 cycle relocated the feeder rules to 705.12(A), which renumbered the busbar methods down a level. The math is identical across cycles; only the citation changed. Always cite the section for the edition your AHJ has actually adopted.
- How do you calculate the 120% rule on a 200A panel?
- Multiply the busbar rating by 1.20, then subtract the main breaker rating. On a 200A busbar with a 200A main: 200 × 1.20 = 240A, minus 200A = 40A available for the solar backfeed breaker. Working backward, a 40A breaker supports 32A of continuous inverter output, since 32 × 1.25 = 40. Always confirm the busbar rating from the panel label, because it is not always equal to the main breaker rating.
- Why does the solar breaker have to go at the opposite end of the panel?
- Because the 20% allowance depends on the two sources being physically separated. With the main at one end and the solar backfeed at the other, loads tapping off the bus between them bleed off current, so no single busbar segment ever carries both full source currents at once. Move the solar breaker next to the main and that assumption collapses, so the code requires opposite-end placement and a permanent "do not relocate" label.
- Does the 120% rule apply to a main-lug-only (MLO) panel?
- No. An MLO panel has no main breaker on the busbar to bound the calculation, so the standard 120% rule does not apply. Sources connecting to an MLO panel are evaluated under different provisions, often supply-side or feeder logic depending on the panel's place in the system. Identify whether a panel is main-breaker or main-lug-only before running any 120% math.
- What is the 125% multiplier and why is it required?
- It is the continuous-current factor from NEC 690.8. Solar output is treated as a continuous load, so you size the backfeed breaker to at least 125% of the inverter's continuous output current. Omitting the 125% multiplier is one of the most common plan-check redlines on the 120% calculation, so it must appear explicitly in the documented math, not just in the final breaker size.
- What happens if my design fails the 120% rule?
- You have options before a service upgrade: derate the main breaker if the Article 220 load calculation allows it, use the sum-of-breakers method, connect to a feeder, tap on the supply side under 705.11, or use a listed Power Control System or EMS under 705.13. A failed 120% calculation usually means the backfeed is too large for the current panel configuration, not that the whole service is undersized.
- Is the 120% busbar calculation the same as a service load calculation?
- No. The 705.12 busbar calculation is a hardware check on whether the busbar can carry combined source current without overheating. The Article 220 service load calculation determines whether the service is sized for the home's total demand. A design can pass one and fail the other, so both have to be checked, and they lead to two different customer conversations.
- Does the 120% rule apply to subpanels?
- Yes. It applies to every busbar in the backfeed path. When a backfed main panel feeds a subpanel, the feed-through conductors and the subpanel busbar must be rated for the combined utility-plus-PV current. Each panel in series between the interconnection point and the service must satisfy one of the 705.12(B) methods, though not necessarily the same one.
- How does adding a battery affect the 120% rule?
- In most AC-coupled systems the battery inverter is a second interactive source, not a load, so it is evaluated independently under 705.12 alongside the PV inverter. Both count against the busbar. Treating the battery inverter as an appliance load is a common retrofit error, and the combined backfeed often pushes the design toward an EMS or PCS path under 705.13.
- Can I avoid a panel upgrade with a 225A busbar?
- Often, yes, on new construction or a full panel replacement. A 225A busbar with a 200A main allows a 50A backfeed breaker versus 40A on a standard 200A/200A panel, which is 8A more continuous PV output. It costs little extra and is the cheapest form of headroom because you design it in rather than retrofitting it later.
The takeaway
The 120% rule is simple arithmetic resting on a real physical constraint: the busbar can only carry so much combined current, and the rule guarantees it never carries more. The two places designers go wrong are precision and propagation. Precision means the right 125% multiplier, the verified busbar rating, the correct breaker placement, and the code citation that matches the adopted cycle, which as of 2023 is 705.12(B)(2), not the 2020 number that many guides still print. Propagation means remembering that the rule follows the current through every busbar in the backfeed path, not just the main panel.
Get those right at the design stage and the 120% rule stops being a source of redlines and becomes what it should be: a quick screening calculation that tells you, before you ever submit, exactly what the panel can accept and which path to take when it cannot.
The 120% busbar check, run on every planset.
Solar Design Lab applies the 125% factor automatically, uses the busbar rating as the controlling value, checks every busbar in the backfeed path, and cites the right 705.12 subsection for your adopted code cycle. $50 per planset, flat.
More resources
Related guides & tools
This guide reflects NEC 705.12 across the 2014, 2017, 2020, and 2023 cycles and manufacturer documentation as of May 2026. Code adoption varies by jurisdiction, and subsection numbering changed between cycles. This is an educational overview, not a substitute for project-specific engineering or the adopted code text. Confirm the adopted code cycle, the AHJ's requirements, and the panel's listed busbar rating for every project.